An FAA PMA part is an article produced under a Parts Manufacturer Approval, which is a combined design and production approval issued by the FAA for a replacement or modification article intended for installation on an identified type-certificated product. It is an approval of a design and of the system that produces it, not a certificate of equivalence to the original part, and that distinction is where most of the industry’s arguments about PMA begin.

The term gets used loosely in two opposite directions. One camp treats a PMA part as an unauthorized copy, which the regulation does not support. The other treats it as interchangeable with the original in every respect and every jurisdiction, which the bilateral arrangements do not support either. What follows is what the regulation itself says, section by section.

Knowing this precisely matters because ⟦PILAR⟧ a PMA is one of the two routes available when a part number can no longer be sourced, and the wrong assumption about what it approves is expensive at exactly the wrong moment.

Where Eligibility Actually Begins

The rule that lets a PMA part be installed is not in the PMA subpart, which is why so many discussions of the subject start in the wrong place.

§21.9 is the gate

14 CFR §21.9, “Replacement and modification articles,” enumerates the conditions under which a person who produces a replacement or modification article for a type-certificated product may make that article available for installation. Paragraph (a)(2) covers an article “Produced under an FAA production approval.”

That is the connection that makes the whole mechanism work. Without §21.9, a PMA would be an approval without a purpose.

A PMA is one of three forms of production approval

Section 21.1(b) states that a production approval “can take the form of a production certificate, a PMA, or a TSO authorization.” The same paragraph defines a design approval as “a type certificate … or the approved design under a PMA, TSO authorization, letter of TSO design approval, or other approved design.”

Read those two definitions together and the architecture is clear. A PMA appears on both lists, which is exactly what makes it unusual: it is a single instrument carrying both a design approval and a production approval. ⟦SAT #4⟧ How that compares with a TSO authorization and with an OEM part is a different question with a different answer.

What Part 21 Subpart K Actually Requires

The subpart is short, specific and rarely read by the people who argue about its output.

Thirteen sections, and what they cover

Part 21 Subpart K, “Parts Manufacturer Approvals,” runs from §21.301 to §21.320 in thirteen sections: applicability, application, organization, quality system, quality manual, location of or change to manufacturing facilities, inspections and tests, issuance, duration, transferability, responsibility of holder, design changes, and changes in quality system.

Two things are worth noticing about that list. There is no eligibility section, which is why §21.9 does the gating. And there is no privileges section either, unlike the TSO subpart, which has one covering approval for deviation.

What the list does contain is a production-quality spine. Four consecutive sections — organization, quality system, quality manual, and location of or change to manufacturing facilities — are about the applicant’s operation rather than about the article, and two more at the end, design changes and changes in quality system, govern what happens after the approval is issued. A PMA is not a one-time finding about a drawing. It is an approval of a manufacturing organization that happens to be scoped to an article.

The application, and what it has to contain

Section 21.303 requires the application to carry the identity of the product on which the article is to be installed, the addresses of the manufacturing facilities, the design expressed as drawings and specifications together with dimensions, materials and processes, and the substantiation for that design. Paragraph (b) then obliges the applicant to “make all inspections and tests necessary” to determine conformity to the approved design and conformity of the processes, construction and assembly.

Note the first item on that list. A PMA is tied to an identified product from the application onward, which is the source of the most practical limitation on the whole instrument.

Note the last one as well. The obligation in paragraph (b) is not to submit a design and wait: it is to determine, by the applicant’s own inspections and tests, that the design complies, that the materials conform, that articles conform to the approved design, and that the processes, construction and assembly conform too. Four separate conformity questions, all placed on the applicant. That is why a serious PMA package is thicker than a drawing set, and why the holder’s quality system is inseparable from the approval itself.

The FAA’s own access to the operation

Section 21.310 provides that the holder “must allow the FAA to inspect its quality system, facilities, technical data, and any manufactured articles and witness any tests.” The same section bars presenting an article for FAA inspection until compliance has been shown, and bars changing the article between that showing and the inspection.

A PMA is therefore not a document that arrives and sits in a drawer. It is a continuing relationship with a quality system attached, and ⟦SAT #2⟧ the route by which the design was substantiated determines a good deal of what that relationship involves.

The Three Features That Surprise People

Each of these is one sentence in the regulation, and each contradicts a common assumption.

A PMA does not expire

Section 21.313 states that a PMA “is effective until surrendered, withdrawn, or the FAA otherwise terminates it.” There is no renewal date and no expiry to diarise.

That is a genuine difference from most of the certificates a maintenance organization tracks. A PMA is not on a calendar. It is on a condition.

A PMA cannot be transferred

Section 21.314 is one sentence: “The holder of a PMA may not transfer the PMA.” An approval does not follow an asset sale, a merger or a change of ownership the way a lease or a registration might.

This has a practical consequence for anyone building a long-term sourcing plan around a single supplier. The approval is attached to the holder, not to the part number, and it does not survive the holder by inheritance.

The holder carries continuing obligations

Section 21.316 places continuing duties on the holder: maintaining the approved quality system, ensuring each article conforms to its approved design and is in a condition for safe operation, marking articles in accordance with Part 45, retaining access to design data sufficient to determine conformity and airworthiness, and keeping the PMA available to the FAA.

That last item about design data is easy to skip and worth pausing on. A PMA holder is expected to be able to determine conformity, which means holding the data rather than merely having held it once.

Two further sections keep the approval current rather than static. Section 21.319 governs design changes and §21.320 governs changes in the quality system, so neither the article nor the operation that produces it can drift away from what was approved without the change itself being handled. A PMA that was correct at issuance and has quietly diverged since is not a PMA in good standing. This is also the answer to the common assumption that a PMA is a one-off transaction: the sections on duration and transferability say the approval does not lapse and does not move, and the sections on changes say it does not stand still either.

How a PMA Article Is Marked

Marking is the part of this a receiving inspector can act on without a data package, and the requirement is shorter than most people expect.

Two elements, both permanent

14 CFR §45.15, “Marking requirements for PMA articles, TSO articles, and Critical parts,” requires the manufacturer to permanently and legibly mark each PMA article with “the PMA holder’s name, trademark, symbol, or other FAA approved identification and part number” and with “The letters ‘FAA-PMA’.”

That is the whole requirement for a standard article: identification plus part number, and the four characters. Anything less invites a question, and ⟦SAT #13⟧ an article whose marking does not match its paperwork is the classic profile of a suspected unapproved part.

Critical parts and the small-part relief

Paragraph (c) adds a unique serial number for critical parts. Paragraph (d) handles the awkward case: where the FAA finds a part or article “too small or otherwise impractical to mark” with the required information, the manufacturer must attach that information to the part or its container instead.

The relief is real and it is documented. An unmarked article with no documented relief is a different situation from an unmarked article with it, and ⟦SAT #3⟧ what the marking has to show at receiving is the shortest useful checklist in this subject. Do not confuse §45.15 with §45.16, which governs the marking of life-limited parts and is a separate obligation.

What a PMA Does Not Do

Three limits are worth stating plainly, because the instrument is routinely described as more universal than it is.

It does not authorize installation on any product

A PMA is approved in connection with an identified type-certificated product, and §21.311 provides that the FAA issues it after finding that the design complies with the requirements applicable to the product on which the article is to be installed. A PMA is a design and production approval tied to a product. It is not a licence to install the article on anything else.

Checking that the approval covers your configuration, not merely your part number, is a five-minute question that occasionally saves a rejected installation. Part numbers migrate across models and variants in ways that approvals do not always follow, so a matching number is evidence that the question is worth asking rather than evidence that it has been answered.

It does not travel automatically to Europe

Acceptance by the European Union Aviation Safety Agency is conditional. The Technical Implementation Procedures between the FAA and EASA, Revision 7 with Amendment 1 incorporated, provide for direct acceptance without further showing in defined cases, and attach additional conditions to others depending on whether the article is a critical component and how its design was substantiated.

⟦SAT #9⟧ Which of those cases applies to a specific part number is a question to settle before a purchase order rather than after an installation is refused.

It does not extend anything the manufacturer’s data limits

A PMA decides who may produce an article. It does not extend a life limit, it does not alter an airworthiness limitation, and it does not make a component repairable beyond the limits published in the manufacturer’s data. Approval mechanisms answer the question of authority. They do not answer the question of how long a part may live.

Questions to Ask Before You Accept a PMA Article

These are the questions that make two offers comparable, and none of them is answered by a price.

Questions about the approval itself

Who holds the PMA, and for which type-certificated product is it approved? Does that approval cover the configuration on your aircraft, and not merely the part number? By which route was the design substantiated, and is the holder able to say so? And is the holder the party you are buying from, or a link further down a distribution chain?

Questions about the article in front of you

Does the article carry the holder’s identification, the part number and the letters “FAA-PMA,” permanently and legibly? If it is not marked directly, what documented relief under §45.15(d) applies, and is the information attached to the article or its container? Is it a critical part, and does it carry the serial number that paragraph (c) requires? And does the traceability go back further than the current seller?

Frequently Asked Questions

what does PMA stand for in aviation?

Parts Manufacturer Approval. It is a combined design and production approval issued by the FAA under Part 21 Subpart K for a replacement or modification article intended for installation on an identified type-certificated product. Section 21.1(b) lists it as one of the three forms a production approval can take.

is a PMA part the same as an aftermarket copy?

No, and the framing is misleading in both directions. A PMA article is produced under an FAA design and production approval, with an approved design, a quality system and a marking obligation attached. What it is not is an article guaranteed to be identical to the original in every respect, since one of the recognized approval routes substantiates the design by test and computation rather than by identicality.

how long does a PMA last?

Indefinitely, subject to conditions. Section 21.313 states that a PMA is effective until surrendered, withdrawn, or otherwise terminated by the FAA. There is no renewal cycle, which also means there is no expiry date to point at as evidence of currency.

can a PMA be bought or transferred with a business?

Not the approval itself. Section 21.314 provides that the holder of a PMA may not transfer the PMA. That has real consequences for sourcing plans built around one supplier, because the approval is attached to the holder rather than to the part number.

how is a PMA part marked?

Under §45.15, permanently and legibly, with the PMA holder’s name, trademark, symbol or other FAA-approved identification together with the part number, and with the letters “FAA-PMA.” Critical parts also carry a unique serial number, and where the FAA finds an article too small or otherwise impractical to mark, the information is attached to the article or its container instead.

will a PMA part be accepted outside the United States?

Not automatically. Under the Technical Implementation Procedures between the FAA and EASA, direct acceptance applies in defined cases, principally for articles that are not critical components and whose design was approved by identicality without a licensing agreement or by test and computation. Other cases carry conditions tied to EASA validation, so the acceptance question belongs before the purchase order.


A PMA is a narrower instrument than its reputation in both directions: it is a real design and production approval, and it is tied to a product, to a holder and to a substantiation route. Read those three attachments before treating a PMA article as a drop-in answer to an obsolescence problem.

About AeroKool Aviation. AeroKool Aviation is an FAA-certificated repair station in Hialeah, Florida, specializing in the repair and overhaul of environmental control system components — air cycle machines, cooling turbines, heat exchangers, refrigeration packages, valves and environmental control units — for commercial, regional, business jet, rotorcraft and military operators. The company was founded in 1959 and holds AS9110C and AS9100D registrations, with in-house PMA parts manufacturing and FAA DER repair engineering. Its engineering, manufacturing and repair management programs are described on the site, and component capability is organized by aircraft category, manufacturer, model and component type in the component capability listing, down to individual part numbers such as this air cycle machine for a narrow-body platform.

This article is general technical information about Parts Manufacturer Approval and the marking and eligibility of replacement articles. It is not approved data, it is not a maintenance procedure, and it does not replace the component maintenance manual, structural repair manual, service bulletin, airworthiness directive or other airworthiness data your organization is approved to use. Regulations, advisory material and manufacturer data are revised, and whether a particular approval covers a particular installation depends on the part number, the aircraft configuration, the operator’s approved program and the scope of the repair station’s certificate. Verify the approval basis and the applicable requirements against the current manufacturer data, your own quality system, and a properly authorized DER, an ODA holder or your FAA principal inspector before accepting or installing any article.

Talk to AeroKool Aviation

AeroKool Aviation is an FAA-certificated repair station in Hialeah, Florida, overhauling air cycle machines, cooling turbines, heat exchangers, valves and environmental control units for commercial, regional, business and military operators since 1959, with an AS9110C quality system and in-house PMA and DER engineering. If you have a component on the bench, a repeat removal you cannot explain, or a part number you cannot source, we will tell you what falls inside our ratings and what does not. Request a quote with the part number and the register the aircraft is on, and the answer will name the approval basis.

Address
1495 S.E. 10th Avenue Hialeah, FL 33010-5984
eMail
aerokool@aerokool.com | sales@aerokool.com
Phone
305.887.6912 | 800.458.4255

Scroll to Top

Have Questions Or Need Information?

Please fill out the form below to contact us and we will get back to you as soon as possible.
Request a Quote
Choose one for Sales and Repair Services
We're committed to your privacy. AeroKool Aviation uses the information you provide to us to contact you about our relevant content, products, and services. You may unsubscribe from these communications at any time. For more information, check out our Privacy Policy.

Looking for parts?

You can search by Part Number or Aircraft Model

Search for Parts

Browse our extensive inventory

Note: You can search by part number

Your Aircraft

Browse our extensive inventory

Note: You can search by aircraft name